Roads25HH0049

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS- P BURGOS ST-(S00116CB)-CHAINAGE 000-CHAINAGE 011,CHAINAGE 011-CHAINAGE 083, CHAINAGE 083 - CHAINAGE 218, (S00117CB) CHAINAGE 000-CHAINAGE

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS- P BURGOS ST-(S00116CB)-CHAINAGE 000-CHAINAGE 011,CHAINAGE 011-CHAINAGE 083, CHAINAGE 083 - CHAINAGE 218, (S00117CB) CHAINAGE 000-CHAINAGE is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱16,408,888.88. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: POWER FRAME CONST. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱27,095 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25HH0049 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2025-01-18 → 2025-06-07

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS- P BURGOS ST-(S00116CB)-CHAINAGE 000-CHAINAGE 011,CHAINAGE 011-CHAINAGE 083, CHAINAGE 083 - CHAINAGE 218, (S00117CB) CHAINAGE 000-CHAINAGE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱27,095,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Sapangdaku (Package 3) Cebu City, Cebu
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cebu City DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

38 projects · ₱508.8M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF MOMPELLER BRIDGE FLOOD CONTROL STRUCTURE AND SCOUR PROTECTION STRUCTURE, BARANGAY MOMP

Cebu 2nd DEO, Region VII

2024₱29.7M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - AC CORTES AVE-K0008 + 230 - K0009 + 257, (S00395CB) CHAINAGE 000 - CHAINAGE 436, MANDAUE CITY, CEBU

Cebu 6th DEO, Region VII

2022₱29.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - NAGA ULING RD - K0022+(-160) - K0022+(-020), K0030+000 - K0030+569.50, K0027+000 - K0027+415, NAGA CITY, CEBU

Cebu 1st DEO, Region VII

2022₱29.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS- DALAGUETE-MANTALONGON-BADIAN RD - K0095+778- K0096+000

Cebu 2nd DEO, Region VII

2024₱29.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - CONCRETING OF POO-BALUD-CONSOLACION ACCESS ROAD LEADING TO OBONG SPRING, DALAGUETE,

Cebu 2nd DEO, Region VII

2024₱28.9M
Past target date (DPWH On-Going)
No sat.

IMPROVEMENT OF ROAD WITH DRAINAGE SYSTEM AT AGATON SORONO ST. TO SUBA MASULOG-SUBA PANAS ROAD (PHASE 2), BARANGAY SUBABASBAS, LAPU-LAPU CITY, CEBU

Cebu 6th DEO, Region VII

2024₱24.5M
Past target date (DPWH On-Going)
View all 38 projects →

4. Implementation

Contract Amount

₱16,408,888.88

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 20, 2025

Target End

May 30, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)City of CebuCentral
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Storm surgeDetails in Hazard context above.Full hazard check →