Roads20EI0100

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, CSR (K0121+668 - K0122+015), BONGABONG, ORIENTAL MINDORO

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, CSR (K0121+668 - K0122+015), BONGABONG, ORIENTAL MINDORO is a DPWH-tracked public work in Southern Mindoro DEO, Region IV-B. Reported contract value: ₱14,209,992.52. Status: Reported complete (DPWH). Contractor on record: ORIENT STAR CONST INC FORMERLY: ORIENT S. Figures trace to dpwh.

Southern Mindoro DEO, Region IV-B
Region: Region IV-B

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2020 · ₱28,608

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 20EI0100 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-04-25 → 2019-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    CY2023 · other

    Confirmed (exact contract ID) · score 1.00

    COA AAR source ↗

Unit-cost benchmark · Road, cost per km (rehabilitation / reconstruction)

₱40,950,987 per km= 1.5x the Region IV-B median (n=142)

Contract cost ₱14,209,993 ÷ 0.347 km read from the DPWH title (“K0121+668 - K0122+015”; K-post / station range length). National percentile: 79. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, CSR (K0121+668 - K0122+015), BONGABONG, ORIENTAL MINDORO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱28,608,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure in Bongabong River, Mapang Section, Bongabong, Oriental Mindoro
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Southern Mindoro DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

46 projects · ₱1.1B total · 0 flags

4. Implementation

Contract Amount

₱14,209,992.52

Progress

Reported complete (DPWH)

Start Date

December 11, 2020

Target End

June 13, 2021

5. Audit

Confirmed (exact contract ID) · 100%

COA observation (CY2023 audit, Par. 16 Technical defects/deficiencies in infrastructure projects). DPWH's action-plan response to this observation names Contract ID 20EI0100, p. 273. Excerpt: "20EI0101/20EI0100/22EI0046 - The contractors were instructed to closely monitor the minor temperature cracks and was advised to rectify the said cracks if further deterioration"

CY2023 · p.273

Connected records

Where this project sits

Place (PSGC)
MIMAROPA RegionOriental MindoroBongabongHagan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Active faultDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.