GAA 2025 SSP25AA0435

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL RD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHAB OF RD, BARANGAY 2 SAN AGUSTIN, SARRAT, I.N.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL RD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHAB OF RD, BARANGAY 2 SAN AGUSTIN, SARRAT, I.N. is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱4,748,956.41. Status: Past target date (DPWH On-Going). Contractor on record: ABEIAN CONST. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay San Antonio, Sarrat, Ilocos Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Ilocos Norte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,748,956.41

Progress

Past target date (DPWH On-Going)

Start Date

April 8, 2025

Target End

June 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.