Construction of Drainage Structure22OH0019

Drainage Improvement along Remedios St. from Remedios Circle to Singalong St., Malate, Manila Phase II

Drainage Improvement along Remedios St. from Remedios Circle to Singalong St., Malate, Manila Phase II is a DPWH-tracked public work in CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region. Reported contract value: ₱77,169,300.35. Status: Reported complete (DPWH). Contractor on record: TRIPLE 8 CONST & SUPPLY INC FORMERLY TRIPLE 8 CONST & SUPPLY. Figures trace to sumbong.

CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures and Facilities along Earnshaw St., (Estero de San Miguel to A.H. Lacson Ave.) and Antipolo St., (G. Tuazon to Espana Blvd.), Manila City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003009

₱631,774,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0004726

₱116,500,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003052

₱75,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001743

₱5,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱77,169,300.35

Progress

Reported complete (DPWH)

Start Date

February 28, 2022

Target End

November 14, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.