Buildings and Facilities23GJ0083

CONSTRUCTION OF MULTI PURPOSE BUILDING - CONSTRUCTION/COMPLETION) OF MULTIPURPOSE BUILDING, HIBAO-AN NORTE, MANDURRIAO

CONSTRUCTION OF MULTI PURPOSE BUILDING - CONSTRUCTION/COMPLETION) OF MULTIPURPOSE BUILDING, HIBAO-AN NORTE, MANDURRIAO is a DPWH-tracked public work in Iloilo City DEO, Region VI. Reported contract value: ₱2,968,768.76. Status: Reported complete (DPWH). Contractor on record: ABELARDE BUILDERS AND SUPPLY. Figures trace to dpwh.

Iloilo City DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 78%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Jalaur River, Calinog, Iloilo
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Iloilo City DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,968,768.76

Progress

Reported complete (DPWH)

Start Date

May 12, 2023

Target End

June 10, 2023

5. Audit