Roads25B00044

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS ALONG MANILA NORTH RD K0634 + 535 - K0636 + 699

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS ALONG MANILA NORTH RD K0634 + 535 - K0636 + 699 is a DPWH-tracked public work in Region II, Region II. Reported contract value: ₱44,456,811.24. Status: Past target date (DPWH On-Going). Contractor on record: GVDPM CONST CORP FORMERLY: ZM CONSTRUCTIO. Figures trace to dpwh.

Region II, Region II
Region: Region II

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25B00044 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    74% reported · imagery 2022-06-20 → 2022-06-20

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Road, cost per km (widening)

₱20,543,813 per km= 0.7x the Region II median (n=189)

Contract cost ₱44,456,811 ÷ 2.164 km read from the DPWH title (“K0634 + 535 - K0636 + 699”; K-post / station range length). National percentile: 9. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS ALONG MANILA NORTH RD K0634 + 535 - K0636 + 699

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

166 projects · ₱9.9B total · 2 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS - MANILA NORTH RD - K0595 + 000 - K0599 + 810; K0600 + 000 - K0600 + 979.7; K0680+000 - K0682+000; K0684+

Region II, Region II

2024₱224.7M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS, CAPAS-BOTOLAN ROAD (BUENO BRIDGE 1), PROVINCE OF TARLAC

Region III, Region III

2021₱214.2M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING- PRIMARY ROADS - MANILA NORTH RD - K0601 + 074 - K0602 + 349, K0602 + 421 - K0603 + 724, K0611 + 1109 - K0612 +729

Region II, Region II

2024₱204.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MISSING GAPS CONNECTING NR, INCLUDING ROW, CAPAS-BOTOLAN ROAD (ZAMBALES SECTION), INCLUDING ROW, ZAMBALES, PROVINCE OF ZAMBALES

Region III, Region III

2017₱188.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION & MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGES INCLUDING ROW, TO MORE THAN 2-LANES-BARANGOBONG BRIDGE-1 (BO1364LZ) ALONG PANIQUI-CAMILING-WAWA ROAD, TARLAC 1ST LEGISLATIVE DISTRICT PROVINCE OF TARLAC

Region III, Region III

2017₱165.1M
Reported complete (DPWH)
No sat.

NATIONAL ROAD AND BRIDGES-RECONSTRUCTION OF LABI BRIDGE ALONG NUEVA ECIJA-AURORA ROAD, BONGABON, NUEVA ECIJA, DAMAGED BY TYPHOON KABAYAN, LANDO AND NONA, PROVINCE OF NUEVA ECIJA

Region III, Region III

2016₱163.5M
Reported complete (DPWH)
View all 166 projects →

4. Implementation

Contract Amount

₱44,456,811.24

Progress

Past target date (DPWH On-Going)

Start Date

February 27, 2025

Target End

September 13, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region II (Cagayan Valley)CagayanSanchez MiraDagueray
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.