Buildings and Facilities18GN0044

CONSTRUCTION OF TWO (2) UNITS UNIQUE TECHNICAL VOCATIONAL LABORATORY (TVL) WORKSHOP FOR SENIOR HIGH SCHOOL AT VALLADOLID NATIONAL HIGH SCHOOL, VALLADOLID, NEGROS OCCIDENTAL

CONSTRUCTION OF TWO (2) UNITS UNIQUE TECHNICAL VOCATIONAL LABORATORY (TVL) WORKSHOP FOR SENIOR HIGH SCHOOL AT VALLADOLID NATIONAL HIGH SCHOOL, VALLADOLID, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 4th DEO, Negros Island Region. Reported contract value: ₱6,892,181.74. Status: Reported complete (DPWH). Contractor on record: ONE TERRA BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Negros Occidental 4th DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Bank Protection) along Ayungon River with Guimaras Strait as an Outfall including Rechanneling, Widening And Deepening Of Riverbed San Enrique-Ayungin Valladolid Section, Negros Occidental
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-B-18-0027976

₱25,425,000.00 · FY2018

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

86 projects · ₱664.8M total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - TERTIARY ROADS - JCT. PONTEVEDRA - LA CASTELLANA ROAD - K0046+000 - K0047+500

Negros Occidental 4th DEO, Negros Island Region

2024₱53.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - JCT. SAN ENRIQUE - PONTEVEDRA BY-PASS ROAD - K0042+600 - K0045+862, K0045+920 - K0045+962

Negros Occidental 4th DEO, Negros Island Region

2024₱30.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION RECONSTRUCTION UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - JCT. PONTEVEDRA-LA CASTELLANA ROAD, K0045+(-975) -K0045+436, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2020₱26.1M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - JCT. SAN ENRIQUE - PONTEVEDRA BY-PASS ROAD - K0040+(-664) - K0040+575, K0040+585 - K0041+230, K0041+272 - K0042+600

Negros Occidental 4th DEO, Negros Island Region

2025₱25.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REINFORCED CONCRETE DECK GIRDER (RCDG) BRIDGE INCLUDING APPROACHES AND SIDE SLOPE PROTECTION AT BRGY. CANROMA TO SITIO SUA TRINIDAD ROAD, BRGY. DON SALVADOR BENEDICTO, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2023₱24.7M
Reported complete (DPWH)
No sat.

RECONSTRUCTION TO CONCRETE PAVEMENT - JCT. PONTEVEDRA - LA CASTELLANA ROAD, K0045+436 - K0046+545, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2021₱21.7M
Reported complete (DPWH)
View all 86 projects →

4. Implementation

Contract Amount

₱6,892,181.74

Progress

Reported complete (DPWH)

Start Date

July 10, 2018

Target End

October 22, 2018

5. Audit