GAA 2025 OO-225OB0448

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PUMPING STATION) AT BARANGAY BATIS, SAN JUAN CITY

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PUMPING STATION) AT BARANGAY BATIS, SAN JUAN CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱0.00. Status: Past target date (DPWH On-Going). Contractor on record: PRECIOUS CONST. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2025 · ₱23,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱140,388,635 · WAWAO BUILDERS

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    0% reported · imagery 2023-03-06 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PUMPING STATION) AT BARANGAY BATIS, SAN JUAN CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱23,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Flood Control Structure along Ermitaño Creek, Barangay Addition Hills, San Juan City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Metro Manila 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Contract ID No. 25OB0448 - Construction of Flood

₱140,388,634.59 · WAWAO BUILDERS

Contractor

B

258 projects · ₱7.9B total · 0 flags

Other projects by this contractor

No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAMCONVERGENCE & SPECIAL SUPPORT PROGRAMCONSTRUCTION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITYCONSTRUCTION OF 2ID PERIMETER FENCE AND GATE 1 & 2, PHASE 2,CAMP CAPINPIN, TANAY, RIZAL

Region IV-A, Region IV-A

2020₱127.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, SALAPAN ELEMENTARY SCHOOL, SAN JUAN CITY

Metro Manila 1st DEO, National Capital Region

2024₱117.0M
Past target date (DPWH On-Going)
No sat.

CLUSTER 01: CONSTRUCTION OF NEW PUP CAMPUS IN CALOOCAN NORTH, BARANGAY 168, CALOOCAN CITYA. CONSTRUCTION OF NEW POLYTECHNIC UNIVERSITY OF THE PHILIPPINES, BARANGAY 168, CALOOCAN CITYB. CONSTRUCTION OF ADMINISTRATIVE BUILDING - POLYTECHNIC UNIVERSITY

Metro Manila 3rd DEO, National Capital Region

2023₱116.4M
Reported complete (DPWH)
No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF MISSING LINKS/NEW ROADS, TAGAYTAY CALAMBA ROAD VIA CANLUBANG, LAGUNA SECTION, LAGUNA

Region IV-A, Region IV-A

2020₱115.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ALERT MULTI-PURPOSE BUILDING BRGY. MALINTA, VALENZUELA CITY

Metro Manila 3rd DEO, National Capital Region

2020₱100.6M
Reported complete (DPWH)
No sat.

CLUSTER I :A) REPAIR/REHABILITATION/IMPROVEMENT OF LUZONG-TUQUIPA ROAD, BRGYS. LUZONG AND TUQUIPA, LUBA, ABRAB) REPAIR/ REHABILITATION/ IMPROVEMENT OF SITIO CABA-GAYAMAN ROAD, BRGY GAYAMAN, LUBA, ABRAC) REPAIR/REHABILITATION/ IMPROVEMENT OF SABNANGA

Cordillera Administrative Region, Cordillera Administrative Region

2018₱100.0M
Past target date (DPWH On-Going)
View all 258 projects →

4. Implementation

Contract Amount

₱0.00

Progress

Past target date (DPWH On-Going)

Start Date

May 20, 2025

Target End

January 14, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
National Capital Region (NCR)City of San JuanBatis
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.