Roads21FA0054

CLUSTER 25-CONCRETING OF FARM TO MARKET ROADS AT MALILIPOT AND MALINAO, ALBAY ( CONCRETING OF BGRY. SAN ROQUE FMR, BRGY. SAN ROQUE, MALILIPOT, ALBAY)

CLUSTER 25-CONCRETING OF FARM TO MARKET ROADS AT MALILIPOT AND MALINAO, ALBAY ( CONCRETING OF BGRY. SAN ROQUE FMR, BRGY. SAN ROQUE, MALILIPOT, ALBAY) is a DPWH-tracked public work in Albay 1st DEO, Region V. Reported contract value: ₱23,880,000.00. Status: Reported complete (DPWH). Contractor on record: 8AR CONST AND DEVELOPMENT CORP. Figures trace to dpwh.

Albay 1st DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱19,250,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Mitigation and River Control at Tagas River traversing Brgys. Baranghawon, Cobo, Basud, Tagas, Sto. Cristo and San Roque, Tabaco City, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Albay 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱23,880,000.00

Progress

Reported complete (DPWH)

Start Date

July 19, 2021

Target End

January 6, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.