Roads20PE0080

RECONSTRUCTION TO CONCRETE PAVEMENT, 280MM - ALONG CITY LIMIT STO. TOMAS ROAD (S00404LZ)

RECONSTRUCTION TO CONCRETE PAVEMENT, 280MM - ALONG CITY LIMIT STO. TOMAS ROAD (S00404LZ) is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱1,072,888.45. Status: Reported complete (DPWH). Contractor on record: HILLSTONE BUILDERS. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,072,888.45

Progress

Reported complete (DPWH)

Start Date

July 16, 2020

Target End

August 19, 2020

5. Audit