Buildings and Facilities24PC0085

CSSP-BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SABANGAN, CALANASAN, APAYAO

CSSP-BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SABANGAN, CALANASAN, APAYAO is a DPWH-tracked public work in Apayao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱9,746,046.45. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: E C V CONST. Figures trace to dpwh.

Apayao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Poblacion Flood Control Structure, Barangay Poblacion, Calanasan, Apayao
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Apayao 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

67 projects · ₱744.0M total · 0 flags

Other projects by this contractor

No sat.

OO2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS - FLOOD MNGT PROG-CON/REHAB OF FLOOD MITIGATION FACILITIES W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONS OF CABICUNGAN RIVER BASIN FLOOD CONTROL STRUCTURE,DAPPAY SECTION, STA.12+090-STA.12+410(L/S),CAL

Apayao 2nd DEO, Cordillera Administrative Region

2025₱46.5M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM- REHAB/RECONS OF ROADS W/ SLIPS,SLOPES COLLAPSE,& LANDSLIDE-TERTIARY ROADS-CLAVERIA-CALANASAN-KABUGAO RD-K0626+605-K0626+670,K0628+513- K0628+577,K0634+554-K0634+600, K0635+343-K0

Apayao 2nd DEO, Cordillera Administrative Region

2025₱42.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONA LOUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF APAYAO RIVER BASINS AND PRINCI

Apayao 1st DEO, Cordillera Administrative Region

2024₱38.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - APAYAO-ILOCOS NORTE RD - K0647 + 120 - K0647 + 320

Apayao 2nd DEO, Cordillera Administrative Region

2024₱33.1M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - APAYAO-ILOCOS NORTE RD- K0650+700 - K0650+737, K065

Apayao 2nd DEO, Cordillera Administrative Region

2025₱30.2M
Past target date (DPWH On-Going)
No sat.

OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - APAYAO (CALANASAN) - ILOCOS NORTE RD - K0619+650 - K0619+800

Apayao 2nd DEO, Cordillera Administrative Region

2024₱29.3M
Reported complete (100% progress, DPWH status On-Going)
View all 67 projects →

4. Implementation

Contract Amount

₱9,746,046.45

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

October 14, 2024

Target End

July 13, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.