Buildings and Facilities18NI0043

PACKAGE 12- CONST'N OF MULTI-PURPOSE BUILDING, BRGY. SAN ROQUE, MUNICIPALITY OF BAROBO, SDS- CONST'N OF MULTI-PURPOSE BUILDING, BRGY. UNIDAD, MUNICIPALITY OF BAROBO, SDS - COMPLETION OF EVACUATION CENTER, POBLACION, MUNICIPALITY OF BAROBO, SDS

PACKAGE 12- CONST'N OF MULTI-PURPOSE BUILDING, BRGY. SAN ROQUE, MUNICIPALITY OF BAROBO, SDS- CONST'N OF MULTI-PURPOSE BUILDING, BRGY. UNIDAD, MUNICIPALITY OF BAROBO, SDS - COMPLETION OF EVACUATION CENTER, POBLACION, MUNICIPALITY OF BAROBO, SDS is a DPWH-tracked public work in Surigao del Sur 2nd DEO, Region XIII. Reported contract value: ₱4,897,248.01. Status: Reported complete (DPWH). Contractor on record: JIMBERNS BUILDERS. Figures trace to dpwh.

Surigao del Sur 2nd DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱8,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Canal w/Box Culvert) Tigbawan, San Roque, Lingig, Surigao Del Sur
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-18-0009517

₱5,000,000.00 · FY2018

Released to Surigao del Sur 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱4,897,248.01

Progress

Reported complete (DPWH)

Start Date

April 10, 2018

Target End

August 7, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.