Roads25IC0039

CONSTRUCTION OF ROAD, BARANGAY PILIT TO BARANGAY ZONE 4 LEADING TO STA. FE PUBLIC MARKET, STA. FE, LEYTE

CONSTRUCTION OF ROAD, BARANGAY PILIT TO BARANGAY ZONE 4 LEADING TO STA. FE PUBLIC MARKET, STA. FE, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱29,374,997.52. Status: Past target date (DPWH On-Going). Contractor on record: B VICENCIO BUILDERS BVB INC FORMERLY:B VICENCIO CONST. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱29,374,998 · B. VICENCIO BUILDERS (BVB), .

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    67% reported · imagery 2019-04-20 → 2025-11-12

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF ROAD, BARANGAY PILIT TO BARANGAY ZONE 4 LEADING TO STA. FE PUBLIC MARKET, STA. FE, LEYTE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Binongto-an, Tanauan, Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Leyte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

CID No. 25IC0039

₱29,374,997.52 · B. VICENCIO BUILDERS (BVB), .

Award / contract ref: 25IC0039

Contractor

B

358 projects · ₱21.1B total · 2 flags

Other projects by this contractor

No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG DAANG MAHARLIKA (SM) (SN ISIDRO - SAN JUANICO BR) - K0810+134 - K0810+500, K0815+000 - K0815+550, K0817+500 - K

Region VIII, Region VIII

2024₱332.5M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITES - CONSTRUCTION OF JUNCTION NATIONAL ROAD BRGY. CAROLINA, CAN-AVID - DOLORES - MASLOG ROAD, (BRGY. MAGSAYSAY - BRGY. MAGONGBONG - BRGY. GAP-A

Region VIII, Region VIII

2022₱238.6M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION / REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS, CATBALOGAN DIVERSION RD. - KO801+(-850) - KO801+510, SAMAR

Region VIII, Region VIII

2019₱236.4M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) K0695+000 - K0696+178, K0697+217 - K0697+533, K0724+748 - K0726+929, SAMAR 1ST

Region VIII, Region VIII

2024₱214.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TACLOBAN STA. FE - SAN MIGUEL ROAD, LEYTE

Region VIII, Region VIII

2024₱192.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPVT. OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS

Region VII, Region VII

2016₱178.0M
Reported complete (DPWH)
View all 358 projects →

4. Implementation

Contract Amount

₱29,374,997.52

Progress

Past target date (DPWH On-Going)

Start Date

February 27, 2025

Target End

August 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VIII (Eastern Visayas)LeyteSanta FeZone 4 Pob.
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.