Roads25CP0065

CONVERGE. AND SPECIAL SUPPORT PROG. -SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRAT. PUBLIC BLDGS./ FACILITIES - CONST.OF ROAD, PHASE I, SITIO PELON, BARANGAY CAMACH

CONVERGE. AND SPECIAL SUPPORT PROG. -SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRAT. PUBLIC BLDGS./ FACILITIES - CONST.OF ROAD, PHASE I, SITIO PELON, BARANGAY CAMACH is a DPWH-tracked public work in Bulacan 3rd DEO, Region III. Reported contract value: ₱142,578,288.47. Status: Past target date (DPWH On-Going). Contractor on record: FLORDES CONST. Figures trace to dpwh.

Bulacan 3rd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Check Gate), Barangay Tampok and Barangay Santa Monica, Hagonoy, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

333 projects · ₱17.6B total · 0 flags

4. Implementation

Contract Amount

₱142,578,288.47

Progress

Past target date (DPWH On-Going)

Start Date

April 14, 2025

Target End

December 9, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.