Bridges20K00323

CONSTRUCTION OF MIONDAS BRIDGE, MALABANG, LANAO DEL SUR

CONSTRUCTION OF MIONDAS BRIDGE, MALABANG, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱33,144,968.77. Status: Reported complete (DPWH). Contractor on record: D C M CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱33,144,968.77

Progress

Reported complete (DPWH)

Start Date

November 23, 2020

Target End

July 23, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.