GAA 2024 SUCs Infrastructure Projects24E00226

ROMBLON STATE UNIVERSITY- CONSTRUCTION OF THE HEALTH AND WELLNESS BUILDING, PHASE I, ODIONGAN, ROMBLON

ROMBLON STATE UNIVERSITY- CONSTRUCTION OF THE HEALTH AND WELLNESS BUILDING, PHASE I, ODIONGAN, ROMBLON is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱14,055,797.25. Status: Past target date (DPWH On-Going). Contractor on record: PERFORMANCE BUILDERS. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱14,055,797.25

Progress

Past target date (DPWH On-Going)

Start Date

September 11, 2024

Target End

May 22, 2025