CONSTRUCTION OF FARM-TO-MILL ROAD, MERCED SEVILLENO TO MERCED JAVELLANA, PONTEVEDRA, NEGROS OCCIDENTAL

CONSTRUCTION OF FARM-TO-MILL ROAD, MERCED SEVILLENO TO MERCED JAVELLANA, PONTEVEDRA, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 4th DEO, Negros Island Region. Reported contract value: ₱12,505,656.28. Status: Reported complete (DPWH). Contractor on record: ONE TERRA BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Negros Occidental 4th DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of flood mitigation structures along Marayo River, Pontevedra, Negros Occidental
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Negros Occidental 4th DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

86 projects · ₱664.8M total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - TERTIARY ROADS - JCT. PONTEVEDRA - LA CASTELLANA ROAD - K0046+000 - K0047+500

Negros Occidental 4th DEO, Negros Island Region

2024₱53.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - JCT. SAN ENRIQUE - PONTEVEDRA BY-PASS ROAD - K0042+600 - K0045+862, K0045+920 - K0045+962

Negros Occidental 4th DEO, Negros Island Region

2024₱30.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION RECONSTRUCTION UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - JCT. PONTEVEDRA-LA CASTELLANA ROAD, K0045+(-975) -K0045+436, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2020₱26.1M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - JCT. SAN ENRIQUE - PONTEVEDRA BY-PASS ROAD - K0040+(-664) - K0040+575, K0040+585 - K0041+230, K0041+272 - K0042+600

Negros Occidental 4th DEO, Negros Island Region

2025₱25.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REINFORCED CONCRETE DECK GIRDER (RCDG) BRIDGE INCLUDING APPROACHES AND SIDE SLOPE PROTECTION AT BRGY. CANROMA TO SITIO SUA TRINIDAD ROAD, BRGY. DON SALVADOR BENEDICTO, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2023₱24.7M
Reported complete (DPWH)
No sat.

RECONSTRUCTION TO CONCRETE PAVEMENT - JCT. PONTEVEDRA - LA CASTELLANA ROAD, K0045+436 - K0046+545, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2021₱21.7M
Reported complete (DPWH)
View all 86 projects →

4. Implementation

Contract Amount

₱12,505,656.28

Progress

Reported complete (DPWH)

Start Date

November 10, 2022

Target End

February 27, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.