Buildings and Facilities21DC0096

LOCAL PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - LOCAL INFRASTRUCTURE PROGRAM, REHABILITATION OF MULTI - PURPOSE BUILDING IN BARANGAY SAN RAFAEL, STO. TOMAS, BATANGAS

LOCAL PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - LOCAL INFRASTRUCTURE PROGRAM, REHABILITATION OF MULTI - PURPOSE BUILDING IN BARANGAY SAN RAFAEL, STO. TOMAS, BATANGAS is a DPWH-tracked public work in Batangas 3rd DEO, Region IV-A. Reported contract value: ₱958,883.05. Status: Reported complete (DPWH). Contractor on record: JERIS CONST AND SUPPLY. Figures trace to dpwh.

Batangas 3rd DEO, Region IV-A
Region: Region IV-A

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2021 · ₱50,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 21DC0096 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-03-13 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: LOCAL PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - LOCAL INFRASTRUCTURE PROGRAM, REHABILITATION OF MULTI - PURPOSE BUILDING IN BARANGAY SAN RAFAEL, STO. TOMAS, BATANGAS

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures along San Juan River, Tanauan - Sto. Tomas, Batangas
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Batangas 3rd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

153 projects · ₱852.3M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, TANAUAN CITY-STO. TOMAS DIVERSION ROAD VIA SAMPALOCAN ROAD, BATANGAS

Batangas 3rd DEO, Region IV-A

2025₱67.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP), SAN PEDRO - STA. CRUZ ECOTOURISM ROAD LEADING TO NATIONAL SHRINE OF ST. PADRE PIO, ST

Batangas 3rd DEO, Region IV-A

2023₱49.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CLASSROOMS BATCH 1, FOUR STOREY TWENTY CLASSROOM, MALVAR NATIONAL HIGH SCHOOL, MALVA

Batangas 3rd DEO, Region IV-A

2018₱44.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, SAN PEDRO-STA. CRUZ ECOTOURISM ROAD LEADING TO NATIONAL SHRINE OF ST. PADRE PIO, STO. TOMAS, BATANGAS

Batangas 3rd DEO, Region IV-A

2020₱41.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - TERTIARY ROADS, TALISAY-LAUREL-AGONCILLO RD

Batangas 3rd DEO, Region IV-A

2022₱34.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT - ROAD WIDENIND - TERTIARY ROADS, LIPA - BALETE RD

Batangas 3rd DEO, Region IV-A

2021₱28.2M
Reported complete (DPWH)
View all 153 projects →

4. Implementation

Contract Amount

₱958,883.05

Progress

Reported complete (DPWH)

Start Date

February 10, 2021

Target End

April 25, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Cite this record

Love the Philippines. “LOCAL PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - LOCAL INFRASTRUCTURE PROGRAM, REHABILITATION OF MULTI - PURPOSE BUILDING IN BARANGAY SAN RAFAEL, STO. TOMAS, BATANGAS.” Source: DPWH. Data as of October 21, 2026. https://lovethephilippines.com/projects/b7208519-f391-4f1e-b808-51a103995bf6

The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)BatangasCity of Sto. TomasSan Rafael
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.