GAA 2023 DepEd BEFF23PI0094

BEFF-BATCH 1: CONSTRUCTION OF 2STY4CL, SACLIT NATIONAL HIGH SCHOOL, SADANGA, MOUNTAIN PROVINCE

BEFF-BATCH 1: CONSTRUCTION OF 2STY4CL, SACLIT NATIONAL HIGH SCHOOL, SADANGA, MOUNTAIN PROVINCE is a DPWH-tracked public work in Mountain Province 1st DEO, Cordillera Administrative Region. Reported contract value: ₱16,709,112.87. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: HC CASSIW CONST. Figures trace to dpwh.

Mountain Province 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Mitigation Structure, Sao-Malitep along Chico River, Balili, Bontoc, Mountain Province
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Mountain Province 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱16,709,112.87

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

November 13, 2023

Target End

November 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.