Roads17P00019

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) JCT. TALUBIN - BARLIG - NATONIN - PARACELIS - CALACCAD ROAD, K0436+316 - K0438+532

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) JCT. TALUBIN - BARLIG - NATONIN - PARACELIS - CALACCAD ROAD, K0436+316 - K0438+532 is a DPWH-tracked public work in Mountain Province 1st DEO, Cordillera Administrative Region. Reported contract value: ₱93,543,403.67. Status: Reported complete (DPWH). Contractor on record: MG SAMIDAN CONST. Figures trace to dpwh.

Mountain Province 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-17-0010461

₱7,894,582.00 · FY2017

Released to Division of South Cotabato (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

533 projects · ₱51.8B total · 52 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL JCT

Cordillera Administrative Region, Cordillera Administrative Region

2022₱289.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS ITOGON - DALUPIRIP - SN MANUEL BDRY ROADKO275+510 -

Cordillera Administrative Region, Cordillera Administrative Region

2021₱279.9M
Reported complete (DPWH)
No sat.

BAGUIO - BONTOC RD - KO347+520 - KO347+577BAUKO, MT. PROVINCE

Cordillera Administrative Region, Cordillera Administrative Region

2022₱241.3M
Reported complete (DPWH)
No sat.

SPECIAL ROAD PROJECT - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD SAFETY DEVICES ALONG A. SN FERNANDO AIRPORT RD - K0265 + (-273)-K0265 + (-128) - K0266 + 828-K0267 + 015, BARANGAY PAGDALAGAN. BARANGAY SAN VICENTE, BARANGAY

Region I, Region I

2023₱241.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG GOV. BADO DANGWA NATIONAL RD (S00377LZ) KO328+(-085) - KO329+420, (S00376LZ) KO320+100 - KO3

Cordillera Administrative Region, Cordillera Administrative Region

2022₱212.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD, CAMP 1 - TABAAN SUR - TABAAN NORTE - TALOY SUR ROAD TO MARCOS HIGHWAY, TUBA, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱212.3M
Reported complete (DPWH)
View all 533 projects →

4. Implementation

Contract Amount

₱93,543,403.67

Progress

Reported complete (DPWH)

Start Date

March 3, 2017

Target End

January 11, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.