Roads25ID0036

CONSTRUCTION OF CONCRETE ROAD, BARANGAY STO. NIÑO -BARANGAY TOLOSAHAY, JULITA,LEYTE

CONSTRUCTION OF CONCRETE ROAD, BARANGAY STO. NIÑO -BARANGAY TOLOSAHAY, JULITA,LEYTE is a DPWH-tracked public work in Leyte 2nd DEO, Region VIII. Reported contract value: ₱10,760,733.26. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ZGPL CONST. Figures trace to dpwh.

Leyte 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱11,650,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure Protecting Public Infrastructure Facilities Construction of Box Culvert, Barangay Hilabago, Dagami, Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Leyte 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱10,760,733.26

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 24, 2025

Target End

April 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.