GAA 2025 OO-125M00052

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SURALLAH-LAKE SEBU-MAITUM RD - K1799+460 - K1799+580, K1827+970 - K1828+022, LAKE SEBU, SOUTH COTABATO

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SURALLAH-LAKE SEBU-MAITUM RD - K1799+460 - K1799+580, K1827+970 - K1828+022, LAKE SEBU, SOUTH COTABATO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱93,604,304.40. Status: Past target date (DPWH On-Going). Contractor on record: AMPLEX CONST AND SUPPLIES 35090. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 35090

107 projects · ₱3.6B total · 0 flags

4. Implementation

Contract Amount

₱93,604,304.40

Progress

Past target date (DPWH On-Going)

Start Date

August 5, 2025

Target End

March 29, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.