Roads22FB0103

OO1: ASSET PRESERVATION PROGRAM - CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROAD - DAANG MAHARLIKA (LZ) K0514+619 - K0514+765, K0517+639 - K0519+000

OO1: ASSET PRESERVATION PROGRAM - CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROAD - DAANG MAHARLIKA (LZ) K0514+619 - K0514+765, K0517+639 - K0519+000 is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱39,199,762.29. Status: Reported complete (DPWH). Contractor on record: NUMERICAL GATE CONST. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Suha Flood Control Dike in Camalig, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Albay 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

70 projects · ₱2.4B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-DARAGA URBAN TOURISM ECO ROUTE ROAD, ALBAY, DARAGA AND LEGAZPI CITY, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱168.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-DARAGA URBAN TOURISM ECO ROUTE ROAD, ALBAY, BRGY. BUSAY, BRGY. BINITAYAN, BRGY. PAWA, ALBAY (2ND LEGISLATIVE DI

Region V, Region V

2023₱124.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS - GUINOBATAN-JOVELLAR-DONSOL ROAD (ILULUAN - PARIAAN SECTION) LEADING TO PILAR PORT, CAMALIG, ALBAY

Albay 2nd DEO, Region V

2019₱96.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS- CAMALIG BYPASS ROAD INCLUDING DRAINAGE SYSTEMS, ALBAY

Albay 2nd DEO, Region V

2023₱96.5M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, DARAGA URBAN TOURISM ECO ROUTE (DUTERTE) PROJECT, ALBAY, DARAGA, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2020₱86.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION/REHABILITATION OF COTMON-HOYOP-HOYOPAN FLOOD CONTROL SYSTEM, BRGY. COTMON, CAMALIG, ALBAY

Albay 2nd DEO, Region V

2020₱74.8M
Reported complete (DPWH)
View all 70 projects →

4. Implementation

Contract Amount

₱39,199,762.29

Progress

Reported complete (DPWH)

Start Date

April 11, 2022

Target End

January 2, 2023

5. Audit