Buildings and Facilities21HJ0036

CONSTRUCTION OF MULTI-PURPOSE BUILDING (FIRE STATION) IN TAYASAN, NEGROS ORIENTAL

CONSTRUCTION OF MULTI-PURPOSE BUILDING (FIRE STATION) IN TAYASAN, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱4,950,000.00. Status: Reported complete (DPWH). Contractor on record: MAI CONST. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2021 · ₱600

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱4,561,579 · MAI CONSTRUCTION AND SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-01-18 → 2025-11-29

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING (FIRE STATION) IN TAYASAN, NEGROS ORIENTAL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱600,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Tinayunan River, Negros Oriental
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Negros Oriental 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction Project

₱4,561,579.35 · MAI CONSTRUCTION AND SUPPLY

Award / contract ref: 21HJ0036

Contractor

A

169 projects · ₱806.4M total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-TERTIARY ROADS - GUIHULNGAN - BALOC - ISABELA RD - K0117 + 825 - K0118 + 308, K0119 + 000- K0119 + 096, K0119 + 418 - K0119 + 650, K0126 + 029 - K01

Negros Oriental 1st DEO, Negros Island Region

2022₱26.5M
Reported complete (DPWH)
No sat.

BASIC EDUCATIONAL FACILITIES FUND (BEFF)- BATCH 1: CONSTRUCTION OF 2STY8CL SCHOOL BUILDING, DAGOHOY NATIONAL HIGH SCHOOL, DAGOHOY, BOHOL

Bohol 2nd DEO, Region VII

2023₱24.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), CARLOS P. GARCIA, BOHOL (PHASE 3)

Bohol 2nd DEO, Region VII

2024₱19.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF JCT. DUMAGUETE NORTH ROAD

Negros Oriental 1st DEO, Negros Island Region

2025₱14.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON ROAD GRAVEL STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) MABINAY - AYUNGON ROAD, AYUNGON, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2018₱12.9M
Reported complete (DPWH)
No sat.

REHABILITATION (COMPLETION) OF DPWH BOHOL 2ND DEO INCLUDING OTHER FACILITIES, UBAY, BOHOL

Bohol 2nd DEO, Region VII

2023₱12.7M
Reported complete (DPWH)
View all 169 projects →

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Reported complete (DPWH)

Start Date

March 1, 2021

Target End

August 16, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Negros Island Region (NIR)Negros OrientalTayasanPoblacion
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-11-03El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.