Buildings and Facilities25OB0105

CONSTRUCTION OF MULTI-PURPOSE BUILDING (HEALTH CENTER), PHASE 2, BARANGAY ADDITION HILLS, SAN JUAN CITY

CONSTRUCTION OF MULTI-PURPOSE BUILDING (HEALTH CENTER), PHASE 2, BARANGAY ADDITION HILLS, SAN JUAN CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱38,391,995.33. Status: Past target date (DPWH On-Going). Contractor on record: WAWAO BUILDERS. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2025 · ₱23,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱38,391,995 · WAWAO BUILDERS

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    14% reported · imagery 2023-03-06 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING (HEALTH CENTER), PHASE 2, BARANGAY ADDITION HILLS, SAN JUAN CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱23,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Flood Control Structure along Ermitaño Creek, Barangay Addition Hills, San Juan City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Metro Manila 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Contract ID No. 25OB0105 - Construction of Multi

₱38,391,995.33 · WAWAO BUILDERS

Award / contract ref: 25OB0105

Contractor

F

164 projects · ₱9.2B total · 16 flags

4. Implementation

Contract Amount

₱38,391,995.33

Progress

Past target date (DPWH On-Going)

Start Date

February 13, 2025

Target End

December 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
National Capital Region (NCR)City of San JuanAddition Hills
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.