Roads19AD0014

ASSETPRESERVATION-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-TERTIARY ROADS ALONG JCT. CANDON-SALCEDO-DEL PILAR ROAD, K0346+(-057)-K0346+197, K0354+853-K0355+403 & K0355+425-K0355+705, CANDON CITY AND GALIMUYOD, ILOCOS SUR

ASSETPRESERVATION-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-TERTIARY ROADS ALONG JCT. CANDON-SALCEDO-DEL PILAR ROAD, K0346+(-057)-K0346+197, K0354+853-K0355+403 & K0355+425-K0355+705, CANDON CITY AND GALIMUYOD, ILOCOS SUR is a DPWH-tracked public work in Ilocos Sur 2nd DEO, Region I. Reported contract value: ₱38,305,799.47. Status: Reported complete (DPWH). Contractor on record: FIRST NORTHWAY DEVELOPMENT. Figures trace to dpwh.

Ilocos Sur 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-LGRCB-19-0003441

₱2,100,000.00 · FY2019

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

275 projects · ₱5.2B total · 0 flags

4. Implementation

Contract Amount

₱38,305,799.47

Progress

Reported complete (DPWH)

Start Date

July 12, 2019

Target End

March 26, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.