Roads25DD0191

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD INCLUDING DRAINAGE STR

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD INCLUDING DRAINAGE STR is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱19,012,854.39. Status: Past target date (DPWH On-Going). Contractor on record: RANRAC CONST CORP 44301. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Calicanto, San Juan, Batangas
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Batangas 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 44301

47 projects · ₱336.8M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD AT BARANGAY STO. NIÑO, LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱19.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD INCLUDING DRAINAGE AT

Batangas 4th DEO, Region IV-A

2025₱19.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY AGUILA, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2025₱14.6M
Past target date (DPWH On-Going)
No sat.

CONCRETING OF BARANGAY BAWI FMR, BARANGAY BAWI, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱14.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF ROAD INCLUDING DRAINAGE AT BRGY. SAN ISIDRO, LIPA

Batangas 4th DEO, Region IV-A

2023₱14.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY SAN CELESTIN

Batangas 4th DEO, Region IV-A

2025₱13.8M
Reported complete (100% progress, DPWH status On-Going)
View all 47 projects →

4. Implementation

Contract Amount

₱19,012,854.39

Progress

Past target date (DPWH On-Going)

Start Date

June 3, 2025

Target End

November 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.