Roads15DH0123

IMPROVEMENT/WIDENING OF NATIONAL ROADS, SECONDARY ROADS, CALAMBA-STA. CRUZ-FAMY JCT. ROAD (S06099LZ), K0102 + 171 - K0102+885 & K0102 + 930 - K0103 + 534.90

IMPROVEMENT/WIDENING OF NATIONAL ROADS, SECONDARY ROADS, CALAMBA-STA. CRUZ-FAMY JCT. ROAD (S06099LZ), K0102 + 171 - K0102+885 & K0102 + 930 - K0103 + 534.90 is a DPWH-tracked public work in Laguna 1st DEO, Region IV-A. Reported contract value: ₱31,812,839.05. Status: Reported complete (DPWH). Contractor on record: NEWBIG FOUR J CONST INC FORMERLY: FOUR J CONST. Figures trace to dpwh.

Laguna 1st DEO, Region IV-A
Region: Region IV-A

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2016 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROVI-16-0037057 · ₱185,000 · release to the district office, not itemized per project

    Possible match · score 0.61

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱31,812,839 · NEWBIG FOUR J CONSTRUCTION .

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2015-03-03 → 2025-05-12

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Road, cost per km (widening)

₱24,120,736 per km= 0.6x the Region IV-A median (n=330)

Contract cost ₱31,812,839 ÷ 1.319 km read from the DPWH title (“K0102 + 171 - K0102+885; K0102 + 930 - K0103 + 534.90”; K-post / station range length). National percentile: 16. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: IMPROVEMENT/WIDENING OF NATIONAL ROADS, SECONDARY ROADS, CALAMBA-STA. CRUZ-FAMY JCT. ROAD (S06099LZ), K0102 + 171 - K0102+885 & K0102 + 930 - K0103 + 534.90

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Pagsanjan River, Pagsanjan Section, Brgy. Pinagsanjan, Pagsanjan, Laguna
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-16-0037057

₱185,000.00 · FY2016

Released to Don Esteban S. Javellana National High School Re (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Improvement/Widening of National Roads, Secondary

₱31,812,839.05 · NEWBIG FOUR J CONSTRUCTION .

Contractor

C

352 projects · ₱28.1B total · 0 flags

4. Implementation

Contract Amount

₱31,812,839.05

Progress

Reported complete (DPWH)

Start Date

March 28, 2016

Target End

October 18, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)LagunaPaeteQuinale
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.