Roads18NI0003

CONST./IMPROV. OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-ACCESS ROAD LEADING TO TOURISM ENTERPRISE ZONE (TEZ)-RIZAL PORT LEADING TO TURTLE ISLAND, CABGAN & VANISHING ISLAND, BRGY. SUA, BAROBO, SURIGAO DEL SUR

CONST./IMPROV. OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-ACCESS ROAD LEADING TO TOURISM ENTERPRISE ZONE (TEZ)-RIZAL PORT LEADING TO TURTLE ISLAND, CABGAN & VANISHING ISLAND, BRGY. SUA, BAROBO, SURIGAO DEL SUR is a DPWH-tracked public work in Surigao del Sur 2nd DEO, Region XIII. Reported contract value: ₱37,023,404.05. Status: Reported complete (DPWH). Contractor on record: LM CONST AND GEN MARKETING. Figures trace to dpwh.

Surigao del Sur 2nd DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱8,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure w/Box Culvert along Surigao-Davao Coastal Road (Bislig Section), Surigao Del Sur
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-18-0009517

₱5,000,000.00 · FY2018

Released to Surigao del Sur 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

176 projects · ₱2.2B total · 0 flags

4. Implementation

Contract Amount

₱37,023,404.05

Progress

Reported complete (DPWH)

Start Date

March 1, 2018

Target End

August 31, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.