Buildings and Facilities16DB0103

CONSTRUCTION OF 4STY 8CL AT TAAL C/S, TAAL, BATANGAS

CONSTRUCTION OF 4STY 8CL AT TAAL C/S, TAAL, BATANGAS is a DPWH-tracked public work in Batangas 1st DEO, Region IV-A. Reported contract value: ₱14,743,206.84. Status: Reported complete (DPWH). Contractor on record: W RIVERA CONST AND EQUIPT RENTALS INC FORMERLY: W RIVERA CONST. Figures trace to dpwh.

Batangas 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Repair/Maintenance of Flood Control Project along San Juan Laiya Road, Putingbuhangin, Nagsaulay Section, Batangas City
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-16-0025301

₱205,570,000.00 · FY2016

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE FACILITY (COLISEUM) AT PANSOL, POBLACION 4, BAUAN, BATANGAS

Batangas 2nd DEO, Region IV-A

2023₱108.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COMMUNITY CENTER), SAN ISIDRO EVACUATION COMPLEX, BATANGAS CITY, BATANG

Batangas 2nd DEO, Region IV-A

2023₱49.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT SAN ISIDRO EVACUATION COMPLEX, BATANGAS CITY, BATANGAS

Batangas 2nd DEO, Region IV-A

2023₱49.5M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING, POBLACION 4, BAUAN, BATANGAS

Batangas 2nd DEO, Region IV-A

2021₱39.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT

Batangas 2nd DEO, Region IV-A

2020₱39.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF EVACUATION CENTER AT BRGY. LAUREL, SAN PASCUAL, BATANGAS PROVINCE

Region IV-A, Region IV-A

2018₱34.0M
Reported complete (DPWH)
View all 102 projects →

4. Implementation

Contract Amount

₱14,743,206.84

Progress

Reported complete (DPWH)

Start Date

May 24, 2016

Target End

November 19, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.