Roads16PJ0032

CONSTRUCTION/ IMPROVEMENT/ RAHABILITATION OF BARANGAY ADUYUNGAN FMR

CONSTRUCTION/ IMPROVEMENT/ RAHABILITATION OF BARANGAY ADUYUNGAN FMR is a DPWH-tracked public work in Ifugao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱1,978,024.82. Status: Reported complete (DPWH). Contractor on record: LUCKY A CONST CORP. Figures trace to dpwh.

Ifugao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,978,024.82

Progress

Reported complete (DPWH)

Start Date

May 29, 2016

Target End

July 27, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.