Buildings and Facilities22BC0153

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PINILI PHASE 2, ABULUG, CAGAYAN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PINILI PHASE 2, ABULUG, CAGAYAN is a DPWH-tracked public work in Cagayan 2nd DEO, Region II. Reported contract value: ₱49,500,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: CMG JR BUILDERS. Figures trace to dpwh.

Cagayan 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Canayun-Sirit-Dana-ili Flood Control along abulug river, abulug, Cagayan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Cagayan 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

112 projects · ₱2.3B total · 2 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: ROAD WIDENING-PRIMARY ROADS-CAGAYAN VALLEY ROAD; K0531+000-K0533+398, GATTARAN, CAGAYAN

Region II, Region II

2020₱102.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG C

Cagayan 2nd DEO, Region II

2025₱96.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, MARUAYA-DUPITAC-CALAMBEG ESTANCIA ROAD LEADING TO LOWLAND COFFEE CONVERGENCE INITIATIVE PROJECT, BRGY. MARUAYA, PIDDIG, ILOCOS NORTE

Region I, Region I

2018₱93.2M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - AYAGA-STA. MARCELA-FLORA-LASAM RD - K0677+000 - K0678+406

Apayao 2nd DEO, Cordillera Administrative Region

2025₱81.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM- TRIP)- ABULUG- BALLESTEROS BAY VIEW BOULEVARD INCLUDING ACCESS ROAD LEADING TO BEACH RESORTS,

Cagayan 2nd DEO, Region II

2024₱72.2M
Reported complete (DPWH)
No sat.

OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - KABUGAO-PUDTOL-LUNA-CAGAYAN BDRY RD - K0681+473 - K0682+529

Apayao 2nd DEO, Cordillera Administrative Region

2025₱57.1M
Past target date (DPWH On-Going)
View all 112 projects →

4. Implementation

Contract Amount

₱49,500,000.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 25, 2022

Target End

October 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.