Water Provision and Storage17HE0100

CLUSTER II - CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM (RWCS): 1. GUINDARUHAN NHS, BRGY. GUINDARUHAN, MINGLANILLA, 2. TINUBDAN NHS, BRGY. TINUBDAN, SAN FERNANDO, 3. LANTAWAN IHS, BRGY. LANTAWAN, SAN FERNANDO, 4. TONGGO NHS, BRGY. TONGGO, SAN FERNANDO, 5

CLUSTER II - CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM (RWCS): 1. GUINDARUHAN NHS, BRGY. GUINDARUHAN, MINGLANILLA, 2. TINUBDAN NHS, BRGY. TINUBDAN, SAN FERNANDO, 3. LANTAWAN IHS, BRGY. LANTAWAN, SAN FERNANDO, 4. TONGGO NHS, BRGY. TONGGO, SAN FERNANDO, 5 is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱1,910,575.74. Status: Reported complete (DPWH). Contractor on record: BT CONST AND GEN SERVICES. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱20,000 (shared by many projects, not this project's own line)

    Possible match · score 0.79

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROI-17-0001003 · ₱1,575,000 · release to the district office, not itemized per project

    Possible match · score 0.62

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17HE0100 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2015-05-15 → 2025-01-18

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CLUSTER II - CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM (RWCS): 1. GUINDARUHAN NHS, BRGY. GUINDARUHAN, MINGLANILLA, 2. TINUBDAN NHS, BRGY. TINUBDAN, SAN FERNANDO, 3. LANTAWAN IHS, BRGY. LANTAWAN, SAN FERNANDO, 4. TONGGO NHS, BRGY. TONGGO, SAN FERNANDO, 5

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control of Bangon Bridge (Downstream), Poblacion, Cebu
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-17-0001003

₱1,575,000.00 · FY2017

Released to Luna National High To School ent (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,910,575.74

Progress

Reported complete (DPWH)

Start Date

July 20, 2017

Target End

September 27, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)CebuMinglanillaGuindaruhan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.