Roads22G00146

CONSTRUCTION OF PRESIDENT CORAZON C. AQUINO AVE. (S00094PN) - CHAINAGE 2736 - CHAINAGE 3109, CHAINAGE 3830 - CHAINAGE 5223

CONSTRUCTION OF PRESIDENT CORAZON C. AQUINO AVE. (S00094PN) - CHAINAGE 2736 - CHAINAGE 3109, CHAINAGE 3830 - CHAINAGE 5223 is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱135,099,691.66. Status: Reported complete (DPWH). Contractor on record: F GURREA CONST INC. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱135,099,691.66

Progress

Reported complete (DPWH)

Start Date

March 29, 2022

Target End

September 22, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.