GAA 2025 OO-225PF0001

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN AGNO RIVER BASIN: ALONG AGNO RIVER GUEDAY TO BUYAKI SECTION, STA. 8+961 - STA. 9+921 (BS), BUGUIAS, BENGUET

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN AGNO RIVER BASIN: ALONG AGNO RIVER GUEDAY TO BUYAKI SECTION, STA. 8+961 - STA. 9+921 (BS), BUGUIAS, BENGUET is a DPWH-tracked public work in Benguet 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱64,166,915.97. Status: Past target date (DPWH On-Going). Contractor on record: OLSIM CONST. Figures trace to dpwh.

Benguet 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure within Agno River Basin: along Agno River Lamagan to Gueday Section, Sta. 8+366 - Sta. 8+966 (BS), Buguias, Benguet
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Benguet 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

27 projects · ₱538.8M total · 0 flags

4. Implementation

Contract Amount

₱64,166,915.97

Progress

Past target date (DPWH On-Going)

Start Date

March 4, 2025

Target End

December 28, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.