Buildings and Facilities25PJ0057

25PJ0057: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF UBAO ES MULTI-PURPOSE BUILDING, (COMPLETION), UBAO, AGUINALDO, IFUGAO

25PJ0057: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF UBAO ES MULTI-PURPOSE BUILDING, (COMPLETION), UBAO, AGUINALDO, IFUGAO is a DPWH-tracked public work in Ifugao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱1,979,309.31. Status: Past target date (DPWH On-Going). Contractor on record: CNRJ CONST. Figures trace to dpwh.

Ifugao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Poblacion Pakawit Communal Irrigation System (CIS), Tinoc, Ifugao
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Ifugao 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

18 projects · ₱65.4M total · 0 flags

Other projects by this contractor

No sat.

23PJ0053: BASIC EDUCATIONAL FACILITIES FUND (BEFF)-BATCH 1: CONSTRUCTION OF 1STY2CL, BUNINAN PS, MAYOYAO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2023₱5.0M
Reported complete (DPWH)
No sat.

24PJ0049: BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF 1-STOREY 2- CLASSROOM SCHOOL BUILDING IN RUFINO I. CHUNGALAO SCIENCE HIGH SCHOOL, BARANGAY MONGGAYANG, AGUINALDO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2024₱5.0M
Reported complete (DPWH)
No sat.

21PJ0049: LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF BARANGAY MAPAWOY TO BARANGAY BONGAN ROAD, MAPAWOY, MAYOYAO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2021₱5.0M
Reported complete (DPWH)
No sat.

25PJ0040: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY UBAO, AGUINALDO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱4.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONCRETING OF BARANGAY AWAYAN FARM TO MARKET ROAD, BARANGAY AWAYAN, AGUINALDO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2019₱4.9M
Reported complete (DPWH)
No sat.

25PJ0074: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES-CONSTRUCTION OF PUNGOD - GUWATIG TO POMOH

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱4.9M
Past target date (DPWH On-Going)
View all 18 projects →

4. Implementation

Contract Amount

₱1,979,309.31

Progress

Past target date (DPWH On-Going)

Start Date

July 11, 2025

Target End

October 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.