Roads25DB0097

CONVERGENCE & SPECIAL SUPPORT PROG- SUSTAINABLE INFRAS PROJ ALLEVIATING GAPS (SIPAG) -ACCESS RD &/OR BR FROM THE NATL RD/S LEADING TO MAJ/ STRATEGIC PUBLIC BLDGS/ FAC-REHABILITATION OF ROAD AT TUY,BATANGAS(CLUSTER 4) - BARANGAY PUTOL & TALON,TUY BATANGAS

CONVERGENCE & SPECIAL SUPPORT PROG- SUSTAINABLE INFRAS PROJ ALLEVIATING GAPS (SIPAG) -ACCESS RD &/OR BR FROM THE NATL RD/S LEADING TO MAJ/ STRATEGIC PUBLIC BLDGS/ FAC-REHABILITATION OF ROAD AT TUY,BATANGAS(CLUSTER 4) - BARANGAY PUTOL & TALON,TUY BATANGAS is a DPWH-tracked public work in Batangas 1st DEO, Region IV-A. Reported contract value: ₱106,054,326.11. Status: Past target date (DPWH On-Going). Contractor on record: READYCON TRADING. Figures trace to dpwh.

Batangas 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure in the City of Calaca, Batangas
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Batangas 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱106,054,326.11

Progress

Past target date (DPWH On-Going)

Start Date

February 18, 2025

Target End

August 31, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.