Roads24C00135

SUSTAINABLE INFRASTRUCT. PROJ. ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS RDS. AND/OR BRS. FROM THE NATL. RD./S LEADING TO MAJOR/STRATEG. PUBLIC BLDGS./FACILITIES-CONST. OF AMRIS LATERAL A,SAN RAFAEL,BUL.(KATUBIGAN-KALSADA TUNGO SA PATUBIGAN),SAN RAFAEL,BUL.

SUSTAINABLE INFRASTRUCT. PROJ. ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS RDS. AND/OR BRS. FROM THE NATL. RD./S LEADING TO MAJOR/STRATEG. PUBLIC BLDGS./FACILITIES-CONST. OF AMRIS LATERAL A,SAN RAFAEL,BUL.(KATUBIGAN-KALSADA TUNGO SA PATUBIGAN),SAN RAFAEL,BUL. is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱8,317,955.97. Status: Past target date (DPWH On-Going). Contractor on record: EIRISH BUILDERS. Figures trace to dpwh.

Region III, Region III
Region: Region III

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱8,317,956 · EIRISH BUILDERS & SUPPLY INC

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    74% reported · imagery 2017-06-26 → 2025-01-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: SUSTAINABLE INFRASTRUCT. PROJ. ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS RDS. AND/OR BRS. FROM THE NATL. RD./S LEADING TO MAJOR/STRATEG. PUBLIC BLDGS./FACILITIES-CONST. OF AMRIS LATERAL A,SAN RAFAEL,BUL.(KATUBIGAN-KALSADA TUNGO SA PATUBIGAN),SAN RAFAEL,BUL.

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24C00135

₱8,317,955.97 · EIRISH BUILDERS & SUPPLY INC

Award / contract ref: 24C00135

Contractor

C

126 projects · ₱3.4B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF ROAD,PHASE II,SITIO TALAMSI I-SITIO KAMB

Bulacan 3rd DEO, Region III

2025₱142.5M
Past target date (DPWH On-Going)
No sat.

CONVERGE. AND SPECIAL SUPPORT PROG. - SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRAT. PUBLIC BLDGSS/ FACILITIES - CONST.OF ROAD, PHASE I, SITIO TALAMSI I - SITIO KAM

Bulacan 3rd DEO, Region III

2025₱142.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL HALL), ANGAT, BULACAN

Bulacan 2nd DEO, Region III

2023₱117.5M
Reported complete (DPWH)
No sat.

STATE UNIVERSITIES AND COLLEGES (SUCS)-ESTABLISHMENT AND/OR SUPPORT TO THE COLLEGE OF MEDICINES, SAN RAFAEL CAMPUS-BULACAN STATE UNIVERSITY, SAN RAFAEL, BULACAN, PROVINCE OF BULACAN

Region III, Region III

2024₱98.5M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, LONGOS - ZAMORA SECTION, STA. 06+220 - STA. 06+340, MEYCAUAYAN, BULACAN

Bulacan 2nd DEO, Region III

2025₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, CITY COLLEGE OF SAN JOSE DEL MONTE SCHOOL OF NURSING AND ALLIED HEALTH (PHASE 2), BARANGAY MINUYAN PROPER, CITY OF SAN JOSE DEL MONTE, BULACAN

Bulacan 2nd DEO, Region III

2025₱96.0M
Past target date (DPWH On-Going)
View all 126 projects →

4. Implementation

Contract Amount

₱8,317,955.97

Progress

Past target date (DPWH On-Going)

Start Date

December 23, 2024

Target End

February 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)BulacanSan RafaelSampaloc
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.