Buildings and Facilities18LE0070

CONSTRUCTION OF SEAPORT ( ROCK CAUSEWAY WITH STAIR LANDING, RC PLATFORM AND RORO RAMP ON FILL), POBLACION, MALITA, DAVAO OCCIDENTAL

CONSTRUCTION OF SEAPORT ( ROCK CAUSEWAY WITH STAIR LANDING, RC PLATFORM AND RORO RAMP ON FILL), POBLACION, MALITA, DAVAO OCCIDENTAL is a DPWH-tracked public work in Davao Occidental DEO, Region XI. Reported contract value: ₱49,260,245.63. Status: Reported complete (DPWH). Contractor on record: LUCK-WELL CONST DEV'T CORP FORMERLY: LUCKWELL CONST. Figures trace to dpwh.

Davao Occidental DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Concrete Revetment (RC Cut-off Wall) at Poblacion, Malita, Davao Occidental
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-LGRCB-18-0025292

₱50,900,000.00 · FY2018

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

27 projects · ₱1.7B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE & SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. &/OR BR. FR. THE NAT'L. RDS./S LEADING TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF ACCESS RD, BRGY. QUINAWAN, BAGAC TO BRGY. BIAAN, MARIVELES, BA

Region III, Region III

2023₱193.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES-LOCAL ROADS, CONSTRUCTION OF ROAD (PHASE I), BARANGAY QUINAWAN, BAGAC, BATAAN

Region III, Region III

2021₱193.0M
Reported complete (DPWH)
No sat.

CONVERGENCE & SPL. SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. &/OR BRIDGES FR. THE NAT'L. RD./S LEAD. TO MAJ./STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF ACCESS ROADS BRGY. QUINAWAN, BAGAC TO BRGY. BIAAN, MARI

Region III, Region III

2024₱189.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF SEAPORT, BALANGONAN, JOSE ABAD SANTOS, DAVAO OCCIDENTAL

Davao Occidental DEO, Region XI

2019₱144.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS & BRIDGES-LOCAL ROADS-CONSTRUCTION OF ACCESS ROAD (PHASE I), BARANGAY QUINAWAN, BAGAC, BATAAN

Region III, Region III

2021₱144.7M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, UMAGOL RIVER, UPSTREAM, SEGMENT VR-2, BAGAC, BATAAN

Bataan 3rd DEO, Region III

2025₱118.2M
Past target date (DPWH On-Going)
View all 27 projects →

4. Implementation

Contract Amount

₱49,260,245.63

Progress

Reported complete (DPWH)

Start Date

April 11, 2018

Target End

April 5, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.