Buildings and Facilities24J00139

CONSTRUCTION OF HARDENED TYPHOON SHELTER HANGAR FOR FIXED WING AIRCRAFT, AIR COMBAT COMMAND (ACC), EAAB, ZAMBOANGA CITY, PHASE III

CONSTRUCTION OF HARDENED TYPHOON SHELTER HANGAR FOR FIXED WING AIRCRAFT, AIR COMBAT COMMAND (ACC), EAAB, ZAMBOANGA CITY, PHASE III is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱14,466,412.61. Status: Past target date (DPWH On-Going). Contractor on record: LL CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱14,466,412.61

Progress

Past target date (DPWH On-Going)

Start Date

October 4, 2024

Target End

March 2, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.