Buildings and Facilities17EB0093No coordinates published by DPWH

CLUSTER 2017-11- CONSTRUCTION OF VARIOUS MULTIPURPOSE BUILDINGS/MUNICIPAL HALL (LIP): A) BRGY. MALPALON, CALINTAAN, B) BRGY. POBLACION, CALINTAAN, C) BRGY. 6, POBLACION, SAN JOSE, D) BRGY. LOURDES, MAGSAYSAY, E) BRGY. SANTA TERESA, MAGSAYSAY, OCC. MINDORO

CLUSTER 2017-11- CONSTRUCTION OF VARIOUS MULTIPURPOSE BUILDINGS/MUNICIPAL HALL (LIP): A) BRGY. MALPALON, CALINTAAN, B) BRGY. POBLACION, CALINTAAN, C) BRGY. 6, POBLACION, SAN JOSE, D) BRGY. LOURDES, MAGSAYSAY, E) BRGY. SANTA TERESA, MAGSAYSAY, OCC. MINDORO is a DPWH-tracked public work in Mindoro Occidental DEO, Region IV-B. Reported contract value: ₱4,802,379.20. Status: Reported complete (DPWH). Contractor on record: JEENE-SON CONST. Figures trace to dpwh.

Mindoro Occidental DEO, Region IV-B

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: Region IV-B

No before/after satellite images: DPWH has not published map coordinates for this project, so there is no location to image.

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2017 · ₱30,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROVIII-17-0000040 · ₱213,291 · release to the district office, not itemized per project

    Possible match · score 0.68

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17EB0093 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CLUSTER 2017-11- CONSTRUCTION OF VARIOUS MULTIPURPOSE BUILDINGS/MUNICIPAL HALL (LIP): A) BRGY. MALPALON, CALINTAAN, B) BRGY. POBLACION, CALINTAAN, C) BRGY. 6, POBLACION, SAN JOSE, D) BRGY. LOURDES, MAGSAYSAY, E) BRGY. SANTA TERESA, MAGSAYSAY, OCC. MINDORO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Busuanga Flood Control (San Jose Section), San Jose, Occidental Mindoro
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0000040

₱213,291.00 · FY2017

Released to 0008 - Regional Office VIII Ter Oli (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

32 projects · ₱202.4M total · 0 flags

4. Implementation

Contract Amount

₱4,802,379.20

Progress

Reported complete (DPWH)

Start Date

June 9, 2017

Target End

October 6, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
MIMAROPA RegionOccidental Mindoro
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Dry conditions likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.