Roads21BH0154

CONCRETING OF ROAD, BRGY. CABULAY

CONCRETING OF ROAD, BRGY. CABULAY is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱9,900,000.00. Status: Reported complete (DPWH). Contractor on record: JAY ARCIE CONST AND SUPPLY. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2021 · ₱49,000 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 21BH0154 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2021-06-17 → 2025-06-06

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONCRETING OF ROAD, BRGY. CABULAY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱49,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Improvement of Flood Control Structure, Brgy. 2, Jones, Isabela, Sta. 0+000 - Sta. 0+390
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Isabela 4th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

28 projects · ₱679.7M total · 1 flags

Other projects by this contractor

OO2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL PROJECT, BARANGAY DISTRICT 2 (CONTINUATION), GAMU

Isabela 3rd DEO, Region II

2025₱96.4M
Reported complete (DPWH)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF PINACANAUAN RIVER FLOOD CONTROL STRUCTURE, BRGY DISTRICT1

Isabela 3rd DEO, Region II

2025₱96.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) -FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES -CONSTRUCTION OF FLOOD CONTROL STRUCTURE, DISTRICT 1, LUCBAN, BENITO

Isabela 3rd DEO, Region II

2025₱96.0M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COLO RIVER SACRIFICE VALLEY SECTION PHASE 6A, HERMOSA, BATAAN

Bataan 1st DEO, Region III

2025₱94.5M
Past target date (DPWH On-Going)
No sat.

Construction of Pinacanauan River Flood Control Project, Barangay Marannao, San Mariano, Isabela (Phase 2)

SAN MARIANO (ISABELA), ISABELA, Region II

2024₱71.9M
Reported complete (DPWH)
No sat.

Construction of Pinacanauan River Flood Control Project, Barangay Marannao, San Mariano, Isabela (Phase 1)

SAN MARIANO (ISABELA), ISABELA, Region II

2024₱71.9M
Reported complete (DPWH)
View all 28 projects →

4. Implementation

Contract Amount

₱9,900,000.00

Progress

Reported complete (DPWH)

Start Date

January 10, 2022

Target End

April 21, 2022

5. Audit