Roads23IB0084

CONCRETING OF BRGY. ABEJAO TO BRGY. NAPARAAN FMR, BRGY. ABEJAO AND BRGY. NAPARAAN, SALCEDO, EASTERN SAMAR

CONCRETING OF BRGY. ABEJAO TO BRGY. NAPARAAN FMR, BRGY. ABEJAO AND BRGY. NAPARAAN, SALCEDO, EASTERN SAMAR is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱23,879,972.42. Status: Reported complete (DPWH). Contractor on record: FOUR K BUILDERS AND CONST SUPPLIES 40332. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of flood control at Brgy. Dampigan, Dolores E. Samar
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Eastern Samar DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱23,879,972.42

Progress

Reported complete (DPWH)

Start Date

May 16, 2023

Target End

September 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.