Bridges22EI0080

WIDENING OF PERMANENT BRIDGES: BAROC BR. (B00063MR) ALONG CALAPAN SOUTH ROAD, MANSALAY, ORIENTAL MINDORO

WIDENING OF PERMANENT BRIDGES: BAROC BR. (B00063MR) ALONG CALAPAN SOUTH ROAD, MANSALAY, ORIENTAL MINDORO is a DPWH-tracked public work in Southern Mindoro DEO, Region IV-B. Reported contract value: ₱65,618,537.92. Status: Reported complete (DPWH). Contractor on record: ST GERRARD CONST GEN CONTRACTOR & DEVELOPMENT CORP FORMERLY:ST GERRARD CONST. Figures trace to dpwh.

Southern Mindoro DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure Cagancan River, Brgy Don Pedro, Mansalay, Oriental Mindoro
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Southern Mindoro DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

103 projects · ₱10.5B total · 4 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF THE NBI MAIN BUILDING (PHASE I)

National Capital Region, National Capital Region

2023₱447.7M
Past target date (DPWH On-Going)
No sat.

SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239- INSTALLATION OF ROADWAY LIGHTING STRUCTURES AL;ONG PUERTO PRINCESA SDOUTH ROAD, K0147+398-K0180+313 (WITH EXCEPTIONS), PALAWAN

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239- INSTALLATION OF ROADWAY LIGHTING STRUCTURE ALONG PUERTO PRINCESA SOUTH ROAD- K0180+313-K0203+730 (INTERMITTENT SECTIONS), PALAWAN

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, PRIMARY ROADS, DAANG MAHARLIKA (LZ), NUEVA ECIJA 2ND LEGISLATIVE DISTRICT, PROVINCE OF NUEVA ECIJA

Region III, Region III

2017₱289.5M
Reported complete (DPWH)
No sat.

CLUSTER 1: 1. SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF PALO - PASTRANA - STA. FE BY-PASS RD, PACKAGE A 2. SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATION

Region VIII, Region VIII

2025₱289.4M
Ongoing (DPWH-reported)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: CONSTRUCTION OF MISSING LINKS/NEW ROADS -TUGUEGARAO CITY BOULEVARD (PINACANAUAN BRIDGE 2 AND APPROACHES), PHASE 2

Region II, Region II

2023₱285.9M
Past target date (DPWH On-Going)
View all 103 projects →

4. Implementation

Contract Amount

₱65,618,537.92

Progress

Reported complete (DPWH)

Start Date

March 7, 2022

Target End

May 22, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.