Roads16FB0043

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-DM JCT.-LEGAZPI-STO.DOMINGO-TABACO-CAM.SUR BDRY. - K0536+282-K0537+860, K0538+620-K0539+043, LEGAZPI CITY

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-DM JCT.-LEGAZPI-STO.DOMINGO-TABACO-CAM.SUR BDRY. - K0536+282-K0537+860, K0538+620-K0539+043, LEGAZPI CITY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱18,014,552.77. Status: Reported complete (DPWH). Contractor on record: AJAN JEADA INC FORMERLY: JEADA CONST 17869. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 17869

37 projects · ₱1.2B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALONG JCT. NATO-SABANG COASTAL ROAD (SABANG-KAWAYNAN BRIDGE) CAMARINES SUR, SAN JOSE, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2023₱96.5M
Reported complete (DPWH)
No sat.

CSSP - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF DIKE STRUCTURES ALONG TAGAYTAY-QUIRANGAY RIVER PACKAGE 2, CAMALIG, ALBAY

Albay 2nd DEO, Region V

2024₱93.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF SAGÑAY RIVER FLOOD MITIGATION STRUCTURE ALONG BAR

Region V, Region V

2025₱74.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS, DARAGA NORTH CENTRAL SCHOOL 4STY16CL, DARAGA (LOCSIN), ALBAY

Albay 2nd DEO, Region V

2019₱68.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD DIKE STRUCTURE ALONG QUIRANGAY RIVER, PACKAGE 1, BARANGAY QUIRANGAY , CA

Region V, Region V

2025₱67.2M
Past target date (DPWH On-Going)
No sat.

BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF DIKE AND GROUNDSILL, BUDIAO RIVER, DARAGA, ALBAY

Albay 2nd DEO, Region V

2024₱64.3M
Past target date (DPWH On-Going)
View all 37 projects →

4. Implementation

Contract Amount

₱18,014,552.77

Progress

Reported complete (DPWH)

Start Date

May 29, 2016

Target End

October 25, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.