Buildings and Facilities25DE0140

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION/COMPLETION OF TESDA REGIONAL TRAINING CENTER (CALABARZON) BUILDING, P. HERRERA ST., BRGY. 6, BATANGAS

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION/COMPLETION OF TESDA REGIONAL TRAINING CENTER (CALABARZON) BUILDING, P. HERRERA ST., BRGY. 6, BATANGAS is a DPWH-tracked public work in Batangas 2nd DEO, Region IV-A. Reported contract value: ₱28,809,000.00. Status: Past target date (DPWH On-Going). Contractor on record: MARSON CONST. Figures trace to dpwh.

Batangas 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Brgy. New Danglayan, Bauan, Batangas
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Batangas 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

7 projects · ₱73.1M total · 0 flags

Other projects by this contractor

No sat.

BASIC EDUCATIONAL FACILITIES FUND (BEFF) - CONSTRUCTION OF SCHOOL BUILDING, SAN JUAN-STO. NIÑO ELEMENTARY SCHOOL, MABINI, BATANGAS

Batangas 2nd DEO, Region IV-A

2025₱9.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. TUNGAL, SAN LUIS, BATANGAS

Batangas 2nd DEO, Region IV-A

2025₱9.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. BULACAN, MABINI, BATANGAS

Batangas 2nd DEO, Region IV-A

2025₱9.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. BULACAN, MABINI, BATANGAS

Batangas 2nd DEO, Region IV-A

2025₱7.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY MACAWAYAN, TINGLOY, BATANGAS

Batangas 2nd DEO, Region IV-A

2025₱3.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY TALAHIB, TINGLOY, BATANGAS

Batangas 2nd DEO, Region IV-A

2025₱3.8M
Past target date (DPWH On-Going)
View all 7 projects →

4. Implementation

Contract Amount

₱28,809,000.00

Progress

Past target date (DPWH On-Going)

Start Date

May 29, 2025

Target End

December 3, 2025

5. Audit