Buildings and Facilities21MA0034

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SATAN, SHARIFF AGUAK, MAGUINDANAO

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SATAN, SHARIFF AGUAK, MAGUINDANAO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱2,469,465.55. Status: Reported complete (DPWH). Contractor on record: RNS CONST ENGINEERING. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

39 projects · ₱462.4M total · 0 flags

4. Implementation

Contract Amount

₱2,469,465.55

Progress

Reported complete (DPWH)

Start Date

September 28, 2021

Target End

January 25, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.