Water Provision and Storage23GK0194

CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS): 1. DON SIMPLICIO LIZARES ELEMENTARY SCHOOL, BRGY. MATAB-ANG, TALISAY CITY, NEGROS OCCIDENTAL; 2. DON HOMERO H. TANPINCO ELEMENTARY SCHOOL, SILAY CITY, NEGROS OCCIDENTAL; 3. MAJA 1 ELEMENTARY SCHOOL, BRGY

CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS): 1. DON SIMPLICIO LIZARES ELEMENTARY SCHOOL, BRGY. MATAB-ANG, TALISAY CITY, NEGROS OCCIDENTAL; 2. DON HOMERO H. TANPINCO ELEMENTARY SCHOOL, SILAY CITY, NEGROS OCCIDENTAL; 3. MAJA 1 ELEMENTARY SCHOOL, BRGY is a DPWH-tracked public work in Negros Occidental 1st DEO, Negros Island Region. Reported contract value: ₱2,246,320.75. Status: Reported complete (DPWH). Contractor on record: XA CONST. Figures trace to dpwh.

Negros Occidental 1st DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱26,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Matagoy Creek, Silay City, Negros Occidental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Negros Occidental 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

39 projects · ₱497.8M total · 2 flags

4. Implementation

Contract Amount

₱2,246,320.75

Progress

Reported complete (DPWH)

Start Date

June 14, 2023

Target End

October 11, 2023

5. Audit