Roads24CC0622

REHABILITATION OF ROAD ALONG GEN. ALEJO SANTOS HIGHWAY, BUSTOS SECTION, BUSTOS, BULACAN

REHABILITATION OF ROAD ALONG GEN. ALEJO SANTOS HIGHWAY, BUSTOS SECTION, BUSTOS, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱46,564,750.84. Status: Past target date (DPWH On-Going). Contractor on record: G D L CONST. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Guiguinto Flood Control Structure, Pritil Section, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bulacan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

62 projects · ₱2.5B total · 0 flags

4. Implementation

Contract Amount

₱46,564,750.84

Progress

Past target date (DPWH On-Going)

Start Date

January 6, 2025

Target End

July 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.