Roads22EB0014

CONSTRUCTION OF CONCRETE ROAD - JUNCTION MWCR (LABANAGN) - MURTHA - JCT IRIRON ROAD, OCCIDENTAL MINDORO

CONSTRUCTION OF CONCRETE ROAD - JUNCTION MWCR (LABANAGN) - MURTHA - JCT IRIRON ROAD, OCCIDENTAL MINDORO is a DPWH-tracked public work in Mindoro Occidental DEO, Region IV-B. Reported contract value: ₱40,080,346.10. Status: Reported complete (DPWH). Contractor on record: F A TORRES CONST. Figures trace to dpwh.

Mindoro Occidental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Callejon Flood Control Structure, Abra de Ilog, Occidental Mindoro
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Mindoro Occidental DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

70 projects · ₱2.1B total · 0 flags

4. Implementation

Contract Amount

₱40,080,346.10

Progress

Reported complete (DPWH)

Start Date

February 28, 2022

Target End

October 6, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.